On Wed, 2004-09-29 at 21:25 -0400, Aaron Bentley wrote:
> If you want it yesterday:
> tla get --link foo--bar--0--patch-53 temp
> tla sync-tree -d temp foo--bar--0--patch-54
> tla apply-delta foo--bar--0--patch-53 temp $ACTUAL_TREE
> rm -R temp

That will not catch patchlog removal.

The "forget" command in tlash (in the tlash.d/features file) is a proof
of concept implementing the --only-changeset feature using only tla
operators.

It's unusably slow and clumsy, but it's a proof of concept.

-- 
                                                            -- ddaa