Description: | Today we can have start and end dates on a project task. Adding a duration and unit will allow tasks to be planified on 2 weeks for example, but having a duration of 2 days.
This will also allow to have a report showing task planified duration, task real time spent and help estimate next similar tasks. |
Priority: | 5 - Medium | | Open to Any Developer: | No |
Subproject: | Module Project | | Assigned to (multiple): | HENRY Florian (fhenry) |
Planned for version: | | | Status |
Start Date: | - | | End Date: | - |
Completion (0-100%): | 100 | | Status: | Closed |
Comments- HENRY Florian 2013-05-17 10:05
- Pull request sned on Dev branch (hour can be now input freely(test input)
- HENRY Florian 2013-05-14 09:32
- https://github.com/FHenry/dolibarr/commit/760ae88f39caa09042bf28a20c6e780c19291588#commitcomment-3203412
Wait until Laurent validation. |
|
Open→ Closed