On Fri, 22 Mar 2013 14:24:01 +0100, Riccardo Mottola wrote:
Hi, given the different failures, I retested everything. I Installed ICU on my NetBSD machine, so that calendar tests can be included. Here my setup. NetBSD i386-32, GCC, icu-50 3 failures, two of which I reported yesterday: base/NSCalendar/features-10-7.m: Failed test: features-10-7.m:33 ... -weekOfMonth returns the correct week
I think I understand the test failure now. For the US guys, 2012-12-31 is in the fifth week of month, but in the UK, it is actually the sixth.
Adding [cal setFirstWeekday:1] (where 1 is Sunday) into the code should hopefully fix the problem. Could you please verify that?
-- Luboš Doležel