Hi Sebastian,
>> On Mon, 19 Mar 2012 14:33:17 +0100, Sebastien Vauban said:
> #+COLUMNS: %40ITEM(Task) %6Effort(Estim.){:} * Context
> The question I'm trying to give an answer to is: *what's the
> remaining number of hours (or days) to finish my project*?
I have just been through this myself so I hope I will be able to help.
To exclude DONE items from the columnview I moved the Effort property
out of the way to the Old_Effort property when the state changes to
DONE:
,-----------------------------------------------------------------------------------------------
| (require 'org)
| (defun my-move-effort-if-done ()
| "For TOC style columnview table. Don't want to include DONE
| items in the TODO Effort column so copy Effort to Old_Effort
| property"
| (interactive)
| ( when (string= (org-get-todo-state) "DONE")
| (member (org-get-todo-state) org-done-keywords)
| ;; check if changing to DONE
| (org-entry-put nil "Old_Effort" (org-get-effort))
| ;; get the :Effort: property
| ;(message (format "Got: %s when changin to %s" ( org-get-effort )
(org-get-todo-state)))
| (setq org-clock-effort (org-get-effort))
| (org-entry-delete nil "Effort")))
|
| (setq org-after-todo-state-change-hook nil)
|
| (add-hook 'org-after-todo-state-change-hook
| 'my-move-effort-if-done)
`-----------------------------------------------------------------------------------------------
Unlike your example I made heavy use of inline tasks and also wanted
heading numbers instead of asterisks, so that the final table looks like
a table of contents with estimated times remaining. I had to do some
more things to achieve this and can elaborate if you like.
Myles