On Fri, Jun 20, 2008 at 1:02 AM, Edi Hance wrote:
> How can I get a list of completed tasks and their
> completion dates? I've combed the Info docs and the
> web and could not find how to do it. I would like
> something like C-c a a l, but that only shows me the
> completed tasks for each day. Is there anyway to get a
> nice sorted list like:
>
> CategoryA: DONE Add xyz to the fobnitz <2008-06-10>
> CategoryB: DONE Fix foo in bar program <2008-06-12>
Set up column view with CLOSED. May be llike so:
(setq org-columns-default-format "%65ITEM(Task) %CLOSED")
Then try `C-c a T', input `DONE' at the prompt. It should
list DONE tasks. Switch to column view with 'C-c C-x C-c'.
I think it kinda does what you want.
> Any ideas? I'm using Org-mode version 4.67c, which is
> included with GNU Emacs 22.2.1. Thanks very much.
6.05b has been released.
HTH,